Goulburn Murray Irrigation Area Map

Early Works GMID Map
Click on a region on the map to zoom in and see information about where the Early Works have been carried out.
click on Torrumbarry to zoom inclick on Pyramid Boort to zoom inclick on Rochester to zoom inclick on Central Goulburn to zoom inclick on Murray Valley to zoom inYou must have Java script enabled to use this map.

 

Summary of Early Works Completed - August 2008

Frames installed:

1000 out of 1000

Gates installed:

1000 out of 1000

Access works:

100% completed

Civil engineering works:

100% completed

Coffer dams installed:

100% completed

Channel remediation:

100% completed (5.3kms plastic lining)

Radio communication system upgrade (Murray Valley and Torrumbarry):

7 out of 9 completed. Two to be completed by end of Nov (pending objection to planning permit)

Looking ahead:

Replacing meters (1047 on CG-5-9 by June, 2009) and rationalising meters