Click on a region on the map to zoom in and see information about where the Early Works have been carried out.
You must have Java script enabled to use this map.
Summary of Early Works Completed - August 2008 |
| Frames installed: | 1000 out of 1000 |
| Gates installed: | 1000 out of 1000 |
| Access works: | 100% completed |
| Civil engineering works: | 100% completed |
| Coffer dams installed: | 100% completed |
| Channel remediation: | 100% completed (5.3kms plastic lining) |
| Radio communication system upgrade (Murray Valley and Torrumbarry): | 7 out of 9 completed. Two to be completed by end of Nov (pending objection to planning permit) |
| Looking ahead: | Replacing meters (1047 on CG-5-9 by June, 2009) and rationalising meters |